Summary
McKee Road is finally under construction, and the R Street intersection and BNSF quiet zone projects are moving ahead with Measure C money. The council will set priorities in June.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
Roughly $735,000 remains in the Measure C safe streets retrofit budget, expanded by change order.
Drivers and residents on paved corridors and near rail crossings.
Mentions & discussions (2)
City Council/Public Finance and Economic Development Authority/Parking Authority — November 2, 2026
Staff will update the council on how city road projects are progressing. Residents dealing with construction delays or rough pavement will want to follow this.
Tax Transparency Commission — May 12, 2026
McKee Road is finally under construction, and the R Street intersection and BNSF quiet zone projects are moving ahead with Measure C money. The council will set priorities in June.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Merced
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.